工程造价计算书
课程
设计
领导形象设计圆作业设计ao工艺污水处理厂设计附属工程施工组织设计清扫机器人结构设计
计算过程
1.平整场地
S=31.78*17.24-(3.3-0.24)*(5-0.24)-8.39-5*15.36=448.13m2
2.挖基础土方
?独立基础土方
J1:3个
J2:9个
J3:2个
J4:8个
J5:3个
J6:5个
J7:2个
J8:4个
J9:1个
J10:1个
J11:1个
独立基础土方量:V= 330.35m3
? 带形基础土方
带形基础土方量:V= (3.3-0.78-0.9)×1.0+(3.3-1.0-0.78)×1.0+(3.3-1.0-0.78)×1.0+(3.3-0.93-1.0)×1.0+(3.3-0.
85+3.3-0.85)×1.0+4.2×1.4×2+2.4×1.7+(3.3-0.85)×2+4.5×2×1.4+2.4×1.7=48.35m3×2
=96.7m3
挖基础土方:V=330.35m3+96.7m3=427.05m3
3.土方回填:
V=1.12×3+2.12×9+2.52×2+1.52×8+1.92×3+2.32×5+2.82×2+1.82×4+2.3
×1.3×1+3.02×1.0+3.38×3.0×1.0=161.87m3
V= 427.05-161.87-(45.63+39.89)=179.66m3
4.底层空心砖墙: (填充高度H=3m )
L=(1.8+3.3)*2-0.24=9.96m
V120= 9.96*0.12*3=3.59m3
5. 240厚时:
外墙中心线:L=60.48+52.8=113.28m
构造柱:0.4*28=11.2m
混凝土墙:3.3*7-0.4*3-0.28*2=21.34m
计算墙体的外墙中心线:L=113.28-11.2-21.34=80.74m
扣除门窗面积:11.6+12.3+16.92+14.4+9+14.4+1.8=79.98m
过梁体积:(3.72+4.1+2.82*2+2.4*2+0.5*8)*0.18*0.24=1.67m3
(1.5+1.5+3*0.5)*0.15*0.24=0.162m3
1.67+0.162=1.832m3
V240= (80.74*3-79.98)*0.24-1.832=37.11m3
6. 二层至屋顶
外墙中心线:(3.3*4+2.4+4.2+4.5+3.3)*2+1.3*4+1.2*2*2=125.6m
9. 砖窨井 2座
10.水井
表
关于同志近三年现实表现材料材料类招标技术评分表图表与交易pdf视力表打印pdf用图表说话 pdf
2座
11.阀门井 2座
12.化粪池 2座
13.带形基础
? 宽 1.0m 长a.(3.3-0.85)×4=9.8m
b.3.3-0.78-0.9+(3.3-0.78-1)×2+3.3-1-0.93=6.03m
(1+0.2)×0.1+1×0.6+1.4×0.24=1.056m2
(9.8+6.03)m×1.056m2 =16.77m3
? 宽1.4m 长 (4.2+1.2)×4=21.6m
[(1.4+0.2)×0.1+1.4×0.6+1.4×0.24]=1.336m2
1.336m2×21.6m=28.86m3
?宽 1.7m 长 2.4×2=4.8m
(1.7+0.2)×0.1+1.7×0.6+1.4×0.24=1.546m2
4.8m×1.546m2=7.42m3
?=16.72m3+28.86m3+7.42m3=53m3
14.独立基础,砼用量
J1:3个
3×0.4×1.4×0.4=2.568 m3
×
?J1=2.568m3
()个
J3:2个
J4:8个
J5:3个
J6:5个
J7:2个
J8:4个
J9:1个
J10:1个 2.92×0.3+(0.4×4+0.5)(0.34+0.4×4)×0.3+
(0.8+0.5)(0.34+0.8)×0.3+1.1×0.4×0.4×2=6.00m3
J11:1个 3.28×2.9×0.3+(0.8+0.4×3+0.48)(0.34+0.4×4)×0.3+
0.8×2×(0.34+0.8) ×0.3+1.1×2+0.4×0.4=5.194
?=73.39m3
15.基础梁
JL-1: L1=(3.3+9.68)=12.98m
S1=0.25×0.35=.0.875m2
23 V1=12.98m×0.0875m=1.136m
JL-2: L=(14.2+4.5+3.3)+4.5+4.5+3.3×2+2.4+(3.3×4+2.4)+4.5×
2+(4.5+4.2+3.3) ×3+3.3×2+(2.0+2.309+0.691)=102.2?
S2=0.25×0.3=0.075?
V2=102.2m×0.075m2=7.665m3
16 框架梁砼用量 (梁高算至板底)
?1=7.89m3
(未含悬梁)
共五根,
L1:
弧形:
?2=3.5m3
直悬梁:
0.24×0.25×(1.2-0.2)=0.06m3×9=0.54m3
?3=1.54m3
?=?1+?2+?3= 32m3+1.54m3+3.5m3=37.04m3
17.框架柱 41个
0.4×0.4×41×3.6=23.62m3
18 构造柱 54根 (高度均为圈过梁底下2.5 m)
加工面马牙槎,一个马牙槎体积
V4=0.144+0.00432×12=0.19m3
?=2V1+10V2+8V3+6V4=4.62m3
4.62×2=9.24m3/层 9.24m3×6=55.44m3
19.圈梁
一层 QL1 L=(4.2+4.5+3.3)×4+4.5×2+3.3+4.5×2+3.3×2+
(3.3×4+2.4)=91.5m
QL L=4.5×2+3.3×2=15.6m
V1=91.5×0.24×0.3+15.6×0.24×0.18=7.26m3
二,六层 QL1 L=(4.2+4.5+3.3)+(3.3×4+2.4)+(3.3+2.1+2.4)×2
+(4.2+4.5+3.3)+
(3.3×4+2.4)(4.2+3.3+4.5) ×2=94.8m
QL L=3.3×4+(3.3+2.1+2.4+2.4+2.1)+3.3×2+2.4+3.3×4+
4.2×2+3.3×4+(3.3×4+2.4) ×2+4.2×2=108.9m
V2=(108.9×0.24×0.18+94.8×0.24×0.3)×5=57.65m3
夹层 QL1 L=94.8m
QL L=3.3×5+3.3×4+4.2×2+(3.3×4+2.4)×2+3.3×3+
4.2×2+(3.3×4+2.4)=96m
V3=94.8×0.24×0.3+96×0.24×0.18=10.97m3
?=V1+V2+V3=75.88m3
20.过梁
L=(3.72+0.5)+(4.1+0.5)×3+(2.82+0.5)+(2.4+0.5)+(2.4+0.5)
+(2.82+0.5)+(1.5+0.5)+(4.1+0.5)+(4.1+0.5)+(1.5+0.5)+
(0.7+0.5)×20+(0.8+0.5)×20+(0.9+0.5) ×55+(0.9+0.5)×55
+(0.9+0.5)×20+(0.9+0.5)×2 =203.86m
V=203.86m×0.24m×0.24m=11.76m3
21 剪力墙(200宽)
{(3.3-0.2) ×2+(4.2+1.2) ×2+2.4] ×2+(3.3-0.48) ×2+(1.6-0.2) ×2}×0.2×3.6=34.01
m3
22.无梁板 (板厚300)
(3.3×4+2.4+0.24)(4.2+4.5+3.3+0.24)+1.2×4.8-2.4×(4.2+1.2+0.24) -27×0.24×0.24×2=369.1m2
2,3,4,5,6 369.1m2×5=1845.5m2
夹层 (3.3×2+1.2+0.24)×4.5+3.5[3.3+(2.1+0.24)]-8×0.24×0.24
=55.46m2×4=221.84m2
板厚
23.有梁板 (板厚600)
右=(3.3×4+2.4)×(4.2+4.5+3.3+0.24)-20×0.4×0.4-[(4.5+1.2)×2 +2.4+
(3.3-0.4-0.1)×2]×2-[(2.4-0.2) ×(4.2+1.2-0.1)]=137.284m2
左=137.284+(4.5+3.3)×(2+2.30+0.691)-0.4-0.4×3+(4.5+2.0+0.5×4.5×3)
=191.554
?=191.554+137.284=328.838m2×0.6m=197.30m3
24.栏板
?阳台栏板V1=199.6×0.12+0.12×0.12×3=27.36m3
?女儿墙 东面 1.3×2×1.2×0.12=0.3744m
西面 (1.2+5.0+1.1+3.3)×1.2×0.12=1.5264m3
北面 (2.4×2×2)×1.2×0.12=1.3824 m3
南面 (3.3×4) ×1.2×0.12=1.9008m3
V栏板=27.36m3+5.18m3=32.54m3
25.楼梯
S(2.24+1.66-0.12)(2.4-0.12)=8.6184
(3.06-0.12)(2.4-0.12)=6.7032
S总= S1+10S2=86.184+6.7032=75.65?
26.散水工程量 (900宽)
(1.2+3.3+4.5+4.2+1.5+3.3×4+2.4+0.9×2+2.4)×0.9=37.05m
27. 任务说明书中已经给出
28. 任务说明书中已经给出
29.玻璃纤维瓦屋面 (屋面-1)
(3.3+4.5+0.3)(3.3×4+2.4)-4.8×(3.3-0.3)=109.08×2=218.16?
30.保温隔热屋面 (屋面-2)
(4.2+0.3)(3.3×4+2.4)+3.3×1.2×2=78.12×2=156.24 ?
31.排水管 17.6×2+17.6+(12.6×2)×2+6.4=74.4m
2 3
32.雨水口 8个
8个 33.雨水斗
34.水泥砂浆地砖地面
S弧形=37π(15-0.24)2/360-9×10/2 =71.455-45=26.455m2
S1=(3.3-0.12)(17.24-0.24×2)=3.18×17.76=53.2968m2
S2=(9-0.12)×2=17.76m2
S3=(4.2+4.5+3.3-0.12)×(3.3+2.4+3.3-0.12)=105.4944m2
S楼梯=[(4.2-0.12+1.2)×2+2.4]×0.24=3.1104m2
S卫生间=(1.8+0.06-0.12)(3.3-0.12-0.06)=5.4288m2
S左=S弧形+ S1+ S2+ S3+ S楼梯+S卫生间=194.467m2
S1=(3.3×2-0.24)(4.2-0.24)=6.36×3.96=25.185m2
S2=(3.3-0.06-0.12)(1.8-0.06-0.12)=5.4288m2
S3=(4.5+3.3-0.12)(3.3+4.5+4.5+3.3-0.24)=7.56×15.36=116.1216m2
S4=(4.2+1.2-0.24)(2.4-0.24)=11.1456m2
S5=(2.4+0.24) ×1.2=3.168m2
S6=S1×2-S2+S3+S4-S5=169.0416m2
S一层=194.467+169.0416=363.5086m2
二层
S=(3.3-0.24)(4.2-0.24)×8+(3.3-0.24)2
×4+[(3.3+2.1+2.4-0.24)(4.5-0.24)-3.168/2]×4=256.88m2 2,3,4,5,6 S2,
6=5S=1284.41m2
S夹=[(3.3+2.4+2.1-0.24)(4.5-0.24)-3.168/2]×4=122.49m2
?=1770.41m2
35水泥砂浆露面
总
36.地砖楼面
S=(2.1-0.24)(3.3-0.24)-0.12×(2.1-0.24)/5.47+
(2.4-0.24)(3.3-0.24)/6.61=12.0776?
2-6层
S总=5S=(5.47+6.61)×2×5×2=241.56 ?
37.踢脚线 高150m
2层以上长度:
夹层:
一层:
算回柱(四面做)
38.水泥砂浆楼梯面
(4.2-0.24)(2.4-0.24)=8.554m2
8.554m2×10+(3.6-0.24)×2.4×2=101.67m2
39.不锈钢栏杆
(2.5×10+0.12+10+1.25)×2=55m
40.水泥砂浆台阶
S=(2.4-0.24)(1.4+2.24)=7.86m2
S总=S×10+S1=78.62+4.51=83.14m2
41.左=[(3.3+0.24)×2×3.5+2.4×3.5+1.2×3.5+(17.24-0.24)×3.5
+(3.3-0.24-0.9×1.2)×2×3.5+(4.2+1.2+1.2)×2×3.5×2
+2×3.5]=210.14 m2
右=2×(4.5+4.2+3.3-0.24)3.5+1.6×3.5×2+(3.3+4.5-0.12
+1.2+4.2) ×2×2=145.84m2
?左+?右=355.98m2
二层[(3.3-0.24)+(4.2-0.24)]×2×2.7-0.9×2.1-1.5×1.5+
(3.3+4.2-0.48) ×2×2.7-0.9×2.1-2.1×2.5+(4.5-0.24+6.6-0.24)
×2×2.7-1.5×1.5-0.9×2.1×4+3×2.7+1.2×2.7×2+(3.3-0.24
+3.3-0.24)×2×2.7-0.9×2.1-1.5×1.5+(2.1-0.24+3.3-0.24)
×2×2.7-0.9×1.5-0.9×2.1×2+(2.4-0.24+3.3-0.24)×2-0.9×2.1 =185.5×4=742.2m2
2,3,4,5,6层 ?=742.2×5=3711m2
夹层 (4.5-0.24+6.6+1.2-0.24)×2×1.7-0.9×2.4-1.5×0.9+1.2×2×
1.7+4.2×1.7+(3.3-0.24+3.3-0.24+2.1-0.24)×2×1.7+
(3.3-0.24+3.3-0.24+2.1-0.24+3.3-0.24) ×2=70.25m2×4
=281m2
?总=355.98+3711+281=4347.98m2
42.厨卫水泥砂浆抹灰
[(2.1+2.4-0.48+3.3-0.24)×2+0.24×(3.3-0.24)]×2.7
-0.7×2.1-0.8×2.1
=37.06 m2×4=148.25m2
?=148.25m2×4=593.1m2
43.外墙抹灰 (外墙×面层高-门窗洞口)
一层 (3.3×2×3.6-0.9×1.2×2)+3.3×3.6+(17.4-2.4-2.4-.24) ×
3.6+17.2×3.6+(4.5+4.2+3.3) ×2×3.6+1.6×2×3.6=230.04m2
2层以上 L外=112.32
112.32×2.8×5-(1.5×1.5×5-0.9×1.5×2) ×2×5=1486.98m2
?=230.04+1486.98=1717.02m2
44. 柱面抹灰工程量计算
柱 截 面 : (400×400)
全抹工程量 : 2×(0.4+0.4) ×3.6×15=86.4m2
[0.4+(0.4-0.24)]×13=7.28m2 抹3面
抹2面 0.4×0.4×13×2=4.16m2
?=97.84m2
45. 阳台楼板 (1.2m高, ? 5.1-9.68×0.12=3.94m2
? (2-0.12+5-0.24)(9-0.24)/2+(3.3-0.24)(5-0.24)=43.65m2
? (12-0.24)(5.6-0.24)×2-(4.2+1.2)(2.4+0.24)×2=332.76m2
2222?+?+?=3.94m+43.65m+332.76m=380.35m
二至六层 ?×5=380.55m2×5=1901.75m2
夹层 (3.3+2.1-0.24)(3.3-0.24)×4
+(4.5-0.24)(3.3×4+2.4-0.24)×2=194.03m2
?=3.94+43.65m2+332.76m2+380.35m2+1901.75m2+194.03m2=2856.48m2
B.4 门窗工程可从门窗图里直接找出。
B.5油漆工程
S外墙面油漆=S外墙抹灰=1717.02m2