迅达电梯3300AP操作安装手册
Schindler 3300 AP
INVENTIO AG
Installation
K 609761 ZH / 06
1-11. SCHINDLER 3300 AP 安装手册
Schindler 3300 AP
Summary 本安装手册描述了Schindler 3300 AP 采用脚手架方法的主要的安装流程。本安装
手册是迅达的机密文件,仅供已培训过的授权人员使用。
Authorization: Authored Reviewed Released
Lead Office: MAP MAP MAP
Name: Yujiqi Xuyi MarkHug
Date: 2009-11-15 2009-12-03 2009-12-16
Modification: 01 02 03 04 05 06
KA No : 591350 561468 591579 591672 591788 591889
KA Date: 05-12-16 06-12-18 2007-09-14 2008-8-16 2009-05-16 2009-12-16
Restrictions This Manual is the property of INVENT IO AG and shall only be used by SCHINDLER personnel or authorized SCHINDLER
agents for purposes which are in the interest of SCHINDLER. This design and information is our intellectual property. W ithout
written consent, it must neither be copied in any manner, nor used for manufacturing, nor communicated to third parties. Applica-
tion for such consent should be addressed to: INV ENT IO AG, Postfach, CH-6052 Hergiswil NW
Page 1 - 288
Schindler 3300 AP
INVENTIO AG
Installation
K 609761 ZH / 06
Contents 1 安全建
议.................................................................................................. 6
1-1 风险管
理......................................................................................... 7
1-2 一般说
明......................................................................................... 8
1-2-1 危
险..................................................................................... 8
1-2-2
警
告..................................................................................... 8
1-2-3 注
意..................................................................................... 8
1-2-4 步
骤..................................................................................... 8
2 带脚手架安装步
骤.................................................................................... 9
3 进场准备,
材料
关于××同志的政审材料调查表环保先进个人材料国家普通话测试材料农民专业合作社注销四查四问剖析材料
接收及
井道检
查............................................................... 11
3-1 安装工
时....................................................................................... 11
3-2 进场准
备....................................................................................... 11
3-3 井道检
查....................................................................................... 12
3-3-1 常规检
查............................................................................ 12
3-3-2 特
别检
查............................................................................ 13
3-4 材料接
收....................................................................................... 16
3-4-1 货物检查与存
贮................................................................. 16
3-4-2 装箱描
述............................................................................ 18
3-5 质量检
查....................................................................................... 19
4 样板
线.................................................................................................... 20
4-1 安装工
时....................................................................................... 20
4-2 样板线概
念.................................................................................... 20
4-3 放样板线步
骤................................................................................ 21
4-3-1 对重框安
装........................................................................ 25
4-4 质量检
查....................................................................................... 34
5 导轨系统安
装......................................................................................... 35
5-1 井道部件介
绍................................................................................ 35
5-2 安装工
时....................................................................................... 36
5-3 支架的定
义.................................................................................... 36
5-4 导轨安装过
程................................................................................ 38
5-4-1 导轨支架概
述..................................................................... 38
5-4-2 导轨支架位置和距
离.......................................................... 46
5-4-3 导轨支架安
装..................................................................... 48
5-4-4 导轨准备工
作..................................................................... 57
5-4-5 底坑组件 (导轨支撑组件)安
装......................................... 61
5-4-6 第一档导轨安
装................................................................. 63
5-4-7 连接
板................................................................................ 66
5-4-8 导轨安
装............................................................................ 67
5-4-9 L 支
架................................................................................ 68
5-5 机房(针对小
机
房)...................................................................... 71
5-6 质量检
查....................................................................................... 73
6 轿厢和对重悬挂装置包
括GBP 限速
器.................................................... 75
6-1 安装工
时....................................................................................... 75
6-2 轿厢悬挂装置
安
装......................................................................... 75
6-3 限速器安
装.........................................................
........................... 77
Copyright 2010 INVENT IO AG
Page 2 - 288
Schindler 3300 AP
INVENTIO AG
Installation
K 609761 ZH / 06
6-4 限速器钢丝绳
安
装......................................................................... 79
6-5 曳引媒介防松
装
置......................................................................... 82
6-6 曳引机支撑安
装............................................................................. 82
6-7 质量检
查....................................................................................... 86
7 厅门安
装................................................................................................ 87
7-1 安装工
时....................................................................................... 87
7-2 厅门安
装....................................................................................... 87
7-3 质量检
查....................................................................................... 88
8 轿厢结构安
装......................................................................................... 89
8-1 安装工
时....................................................................................... 89
8-1-1 准
备工
作............................................................................ 89
8-1-2 轿
厢下梁吊
入..................................................................... 91
8-2 轿厢变
量....................................................................................... 93
8-3 轿厢结构安
装................................................................................ 94
9 机组安
装...............................................................................................121
9-1 安装工
时......................................................................................121
9-2 质量检
查......................................................................................127
10 轿顶护
栏...............................................................................................129
10-1 安装工
时......................................................................................129
10-2 质量检
查......................................................................................132
11 轿门系统安
装........................................................................................134
11-1 安装工
时......................................................................................134
11-2 门地
坎..........................................................................................134
11-3 门机装
配......................................................................................135
11-4 轿门导
靴......................................................................................136
11-5 门板调
整......................................................................................136
11-6 调整检
查......................................................................................137
11-7 门
刀.............................................................................................139
11-8 功能检
查......................................................................................139
11-9 噪音检
查......................................................................................140
11-10门光幕安
装...................................................................................141
11-11电气安
装......................................................................................146
11-12安装顶层厅门和
LDU....................................................................147
11-13质量检
查......................................................................................147
12 主要电气部件安装
Bionic
5.2 ...............................................................149
12-1 安装工
时......................................................................................149
12-2 交流变频器安
装............................................................................149
12-3 LDU 与HCU 安
装........................................................................153
12-4 电源输
入......................................................................................155
12-5 LDU,变频器和
机组之间的电气连
接............................................156
12-6 轿厢电气部件安
装........................................................................165
12-7 随行电
缆......................................................................................167
12-8 质量检
查......................................................................................171
13 主电源 Bionic
5.4 .................................................................................173
Copyright 2010 INVENT IO AG
Page 3 - 288
Schindler 3300 AP
INVENTIO AG
Installation
K 609761 ZH / 06
13-1 安装工
时......................................................................................173
13-2 变频器安
装...................................................................................173
13-3 LDU 和HCU 安
装........................................................................173
13-4 主电源的接
入...............................................................................174
13-5 随行电
缆......................................................................................176
13-6 质量检
查......................................................................................176
14 其它电气工作及井道信
息.......................................................................178
14-1 安装工
时......................................................................................178
14-2 急停开关
JHSK ............................................................................178
14-3 ESE 电线安装
用于
MMR ............................................................181
14-4
BIOBUS .......................................................................................181
14-4-1 BIOBUS 概
述....................................................................181
14-4-2 BIOBUS 安
装....................................................................182
14-5 LOP and LIN ................................................................................182
14-6 LCUX 安
装...................................................................................184
14-7 操纵箱安装
COP ........................................................................185
14-8 井道端站开关
KSE .......................................................................188
14-9 PHS, PHNR-D/U 和PHUET 的安
装.............................................191
14-10井道极限开关装
置
KNE ...............................................................193
14-11质量检
查......................................................................................196
15 缓冲器, 曳引媒介和对
重安
装................................................................198
15-1 安装工
时......................................................................................198
15-2 缓冲器安
装..................................................................................198
15-3 对重准备工
作...............................................................................204
15-4 曳引媒介操作,
注意事
项..............................................................209
15-5 曳引媒介安
装..............................................................................209
15-5-1 准备
工
作...........................................................................209
15-5-2 曳引
媒介安
装....................................................................212
15-5-3 磨擦
力减少区
域................................................................225
15-6 导靴安
装......................................................................................226
15-7 质量检
查......................................................................................228
15-8 护脚
板..........................................................................................229
16 轿壁与轿厢装潢安
装..............................................................................231
16-1 安装工
时......................................................................................231
16-2 装饰吊顶安
装.........................................................
.....................231
16-3 轿厢装
潢......................................................................................233
16-3-1 准备
工
作...........................................................................237
16-4 质量检
查......................................................................................256
17 安全钳和安装运
行.................................................................................257
17-1 安装工
时......................................................................................257
17-2 脚手架拆
除...................................................................................257
17-3 安全钳检
查...................................................................................257
17-4 安装运
行......................................................................................259
17-5 导轨油杯和集
油
盒........................................................................259
17-6 质量检
查......................................................................................260
Copyright 2010 INVENT IO AG
Page 4 - 288
Schindler 3300 AP
INVENTIO AG
Installation
K 609761 ZH / 06
18 收尾工
作...............................................................................................262
18-1 安装工
时......................................................................................262
18-2 灯管及灯
罩...................................................................................262
18-3 厅门收尾调
整...............................................................................264
18-4 轿厢锁
CBD ................................................................................265
18-5 轿厢风
扇......................................................................................267
18-6 轿顶照
明......................................................................................268
18-7 文件
夹..........................................................................................268
18-8 轿顶走
线......................................................................................269
18-9 对重
块..........................................................................................275
18-10对重防护
屏...................................................................................277
18-11适配变压
器...................................................................................278
18-12底坑爬
梯......................................................................................280
18-13底坑急停安
装...............................................................................282
18-14底坑照明开关
JLBS 和底坑插座
PSG ...........................................283
18-15对重安全钳开关
KFG....................................................................284
18-16井道照
明......................................................................................286
18-17质量检
查......................................................................................288
Copyright 2010 INVENT IO AG
Page 5 - 288
Schindler 3300 AP INVENTIO AG
Installation
K 609761 ZH / 06
1 全建议
安全要求 所有有关人员必须熟悉适当的安全措施 (行为,设备)和安全装备的使用。
全装备
1 安全帽 2 防护眼睛
3 全身式安全带 4 安全鞋
5 防护手套
光线要充足以保证工作安全。
损坏或遗失的安全装备 (见图1)必须立
刻替换或补充。
如有跌落的危险,应使用安全绳及安全带加
以保护。
所有工具必须保持良好的使用状态。
当使用机械设备时,请按照设备厂家提供的
使用
说明
关于失联党员情况说明岗位说明总经理岗位说明书会计岗位说明书行政主管岗位说明书
书要求进行操作。
每个工作人员应对自身的安全和健康负 。
Copyright 2010 INVENT IO AG
Page 6 - 288
Schindler 3300 AP
INVENTIO AG
Installation
K 609761 ZH / 06
1-1 风险管理
危险~
在开始工作前,请认真阅读下列风险评估。必须执行所有相关的安全规则。
行为/危险 结果 控制方法 剩余风险管理
伤害眼睛
伤害听力 个人防护用品:防护眼镜,听力保护器,
钻孔 吸入微小颗粒 防尘面罩,手套,工作服, 最小的
飞尘 遵守使用说明书要
求使用工具
伤害手或手腕
急救措施
滑倒,跌倒,跌落 破口,磨损,扭伤,损伤 熟悉环境
最小的
进入底坑时使用爬梯
在脚手架上工作时,使用全身式安全带
在轿顶工作时,使用全身式安全带
从高处坠落 严重伤害, 故
急救措施
在梯子上工作或离底坑高2 米时,使用全身
式安全带
设计、使用工作平台
根据要求,在井道入口处设置防跌落保护
救援程序
物品落入井道 严重伤害, 个人防护用品:安全帽
急救措施
禁止在不同楼层同时
工作
货物失控, 雇用专业公司 急救措施
起重设备失效
严重伤害, 故 检查所有设备 最小的
急救措施
快口,擦伤 破口, 个人防护用品:
手套,安全鞋
最小的
使用机械进行搬运,
人工搬运 严重伤害,
中等的
正确的搬运方法
通过路口 严重伤害, 故 路障,控制
器,反射背心 最小的
绝缘
触电 严重伤害, 故 最小的
上锁,使用标签
Copyright 2010 INVENT IO AG Page 7 - 288
Schindler 3300 AP INVENTIO AG
Installation
K 609761 ZH / 06
1-2 一般说明
1-2-1 危险
下列符号::
危险~
对安装工人或现场其他人员指 其应注意的安全相关的 情:
在进行下一步工作前,请认真地阅读相关内容~
忽略这些信息,将导致危险及/或严重伤害~
1-2-2 警告
下列符号:
警告~
指 应注意的与部件相关的 情:
在进行下一步工作前,请认真地阅读“警告”后的相关内容~
忽略这些信息,将导致部件的损坏或功能的改变。
1-2-3 注意
下列符号:
注意~
指 应注意的与安装相关的 情:
在进行下一步工作前,请认真地阅读“注意”后的相关内容~
忽略这些信息,将导致部件安装的工作效率降低或超时工作。
1-2-4 步骤
下列符号:
No Step
100
101
在某一安装阶段,需执行的安装步骤:
忽略这些信息,将导致部件安装的工作效率降低,超时工作
或不安全的工作环境。
Copyright 2010 INVENT IO AG
Page 8 - 288
Schindler 3300 AP
INVENTIO AG
Installation
K 609761 ZH / 06
2 带脚手架 装步骤
Summary 安装工作必须按照预先定义的安装流程和步骤实施。
安装流程 Schindler 3300 AP 安装流程定义如下:
在开始安装前,需根据土建图对所有土建进行检查,所有材料已到达现场。
在开始安装前,应没有土建问题或材料问题。
发运清单
工厂库房 质量记录
二次确认 发运
否
检查清单
是 货物接收
是
装部门 否 OK?
确认
货物清点 安装 移交
否
SA IS
质量部门
通过
是
维保部门 移交
现场准备
会议纪要 货物检查
客户 移交
脚手架准备 电源准备
政府部门 检验
装流程
安装计划 安装程序建议如下.
1. 安全手续
2. 检查和准备施工现场
3. 脚手架检查
工具 4. 设置样板线
导轨 5. 导轨支架和第一档导轨安装
机械1 6. 对重框及底坑组件安装
导轨+ 机械2 7. 安装其他所有导轨
机械2 8. 轿厢&悬挂装置包括GBP 限速器
门 9. 厅门安装 (除顶层厅门)
工具 10. 轿厢下梁支撑工具安装
轿厢+ 机械1 +
11. 轿厢结构安装
轿顶&轿底地板
前壁 12. 轿厢前壁系统安装
Copyright 2010 INVENT IO AG
Page 9 - 288
Schindler 3300 AP
INVENTIO AG
Installation
K 609761 ZH / 06
工具 13. 轿厢吊梁+机组提升工具
机组 14. 机组安装
轿厢前壁 15. 门机系统, 地坎安装,
厅门 16. LDU 的顶层厅门
电气 17. 安装变频器, 外围设备, 井道信息和其他电气工作
机械1 + 电气+ 对
18. 缓冲器, 曳引媒介安装和对重准备 50% 对重块, … ,护脚板安装
重块
装潢 19. 轿壁板和轿厢装潢安装
工具 20. 脚手架拆除
21. 安装运行
机械1 + 对重块 22. 收尾工作, 对重块和对重防护屏
23. 调试
24. 测试和检验
编号 项目 D D1/D D D D1 D2 D3
D4 D5 D6 D7 D8 D D9 D10 D D
1 安装准备
1.1 脚手架
1.2 样板线
1.3 井道测量+整改
1.4 材料到达
1.5 工程开始会议
2 安装
2.1 导轨安装
2.2 对重框和底坑组件安装
2.3 轿厢和对重悬挂装置
2.4 GBP限速器
2.5 厅门安装 顶层除外
2.6 轿厢结构安装
2.7 轿厢前壁安装
2.8 轿厢吊梁+机组提升工具
2.9 机组安装
2.10 门机,地坎安装
2.11 顶层厅门 LDU
2.12 变频器+随行电缆
2.13 井道接线和其他设备
2.14 曳引媒介+缓冲器+对重块50%
2.15 脚手架拆除
2.16 轿厢装潢安装
2.17 安装运行
2.18 收尾工作
2.19 对重100%和防护屏
2.20 调试和调整
3 检验和移交
3.1 检验
3.2 移交
每日工作表
Note!
根据预先定义的流程执行安装步骤。在未完
成相应的安装和过程检验前,不应进行
下一步的安装工作。如果需要改变任何安装
顺序,请与您的安装监督咨询。
Copyright 2010 INVENT IO AG
Page 10 - 288
Schindler 3300 AP
INVENTIO AG
Installation
K 609761 ZH / 06
3 进场准备, 材料接收及井 检查
Summary 章提供了工地上第一步的详细的说明:
到达现场, 初步井道土建检查
材料接收
材料搬运及存贮
3-1 装工时
安装工时 工时 为: 以800kg, 1.0m/s, 10 层为例
安装人员进场, 现场准备, 初步土建检查 12.0h
脚手架检查
4.0h
特别检查
2.0h
材料接收,搬运及存贮
8.0h
3-2 进场准备
进场准备 编号 步骤
300 安装监督介绍安装工给建筑方主管,说明
安装计划,澄清必要的细节:
更衣室
工作时间表
工地安装规则
协助重物搬运
其它…
Site Visiting
Copyright 2010 INVENT IO AG Page 11 - 288
Schindler 3300 AP INVENTIO AG
Installation
K 609761 ZH / 06
3-3 井 检查
Summary 章包括建筑方相关人员一起执行第一次现场
检查的内容,
已根据 “建筑物检查清单”完成土建检查
及二次确认。
主要目标是评定能在正确的条件下开始电梯安装。
3-3-1 常规检查
Note!
为了向客户提供准时的、高品质的电梯安装工作,清洁和干燥的施工现场的是绝对
有必要的。
常规检查 301 与建筑方一起检查井道,尤其是
防止跌落装置已正确安装到位。
完工后的地坪标高及大楼轴线已定义并清楚标识 1
底坑内没有污水及垃 2
井道尺寸与土建图一致 3
有可使用的电源 4
常规检查
Copyright 2010 INVENT IO AG
Page 12 - 288
Schindler 3300 AP
INVENTIO AG
Installation
K 609761 ZH / 06
3-3-2 特别检查
注意!
“建筑物检查清单”中已定义了现场需具
备的施工条件。
根据土建图,检查现场土建尺寸,并记录不符合项。
特别检查 302 根据实际井道高度检查导轨长度:
测量HQ+HSG 的尺寸 (提升高度+底坑深度)
计算如下尺寸:
[A] HQ + HSG + X - 240mm 对于对重导轨 载重 630kg
[A] HQ + HSG + X - 200mm 对于对重导轨 载重 630kg
[B] HQ + HSG + X [mm] 对于轿厢导轨
X 值应根据土建图决定~下面图只是一个举例。
X L car 从顶层楼面到导轨顶
部长度
将[A] 和[B] 值,与所发运的导轨实
际长度相比较
特别检查
如果“X ”的实际值大于土建图要求的尺
寸,则需要根据J139458 仔
细检查机组马达到井道顶部的距离。
Copyright 2010 INVENT IO AG
Page 13 - 288
Schindler 3300 AP
INVENTIO AG
Installation
K 609761 ZH / 06
警告~
导轨实际安装长度必须与[A]和[B]尺寸相一致~迅达提供
标准
excel标准偏差excel标准偏差函数exl标准差函数国标检验抽样标准表免费下载红头文件格式标准下载
的5m 或2.5m 导轨,
以及专门定制的4.5m,4m,3.5m,3m 导轨 导轨多余部份,应在现场切割。切割时,
应从有槽的一端进行切割。请注意装箱清单内容~
举例 载重 800kg :
井道实际测量
HQ 30000mm
HSG 1400mm
X 3320mm 根据土建图
导轨发运 举例 :
[A] 30000 + 1400 + 3320 -240
34480mm
[B] 30000 + 1400 + 3320 34720mm
Rail delivery example :
对重导轨 :6 根x 5000mm+4500mm 34500mm
轿厢导轨 :7 根x 5000mm
35000mm
这说明,多余的280mm (轿厢导轨)和20mm (对重导轨)需要现场从雌头一端
切割。
Copyright 2010 INVENT IO AG
Page 14 - 288
Schindler 3300 AP
INVENTIO AG
Installation
K 609761 ZH / 06
特别检查 303 根据实际井道高度检查导轨长
度:
测量HQ+HSG 的尺寸 (提升高度+
底坑深度)
对于 MMR 计算如下尺寸:
[A] HQ + HSG + Y - 240mm 对
于对重导轨 载重 630kg
[A] HQ + HSG + Y - 200mm 对于对重导轨 载重 630kg
[B] HQ + HSG + Y [mm] 对于主机侧的轿厢导轨
[C] HQ + HSG + X [mm] 对于限速器侧的轿厢导轨
X、Y 值应根据土建图决定~下面图只是一个举例。
X L car 顶层地面到轿厢导轨顶的长度
Y 顶层高度+ 井道天花板的厚度+ 750
用发来的导轨总长和[A] 、[B] 、[C]的值比较
Special Checking
Copyright 2010 INVENT IO AG
Page 15 - 288
Schindler 3300 AP
INVENTIO AG
Installation
K 609761 ZH / 06
警告~
在切割导轨前,请仔细阅读下面部分的土建图,
特别是下面
表格
关于规范使用各类表格的通知入职表格免费下载关于主播时间做一个表格详细英语字母大小写表格下载简历表格模板下载
导轨实际安装长度必须与[A] ,[B],[C]尺寸
相一致~迅达提供标准的5m 或2.5m 导
轨, 以及专门定制的导轨 导轨多余部份,应在现场切割。切割时,应从有槽的一
端进行切割。
* 根据不同的Lcar 的尺寸, 对于限速器侧的导轨,迅达发3.0/3.1/3.2……/3.9/4m
的导轨.
3-4 材料接收
Summary 章提供了以下部件的详细的安装说明::
检查箱子数量
检查包装情况,没有外部原因的损坏
在干净、干燥,接近井道的安全区域,正确存放货物。
为了便于安装,在底层厅门入口附近,堆
放导轨
如果需要,将机组及轿厢下梁组件运至顶层。
3-4-1 货物检查与存贮
材料接收 304 检查并确认货物的总数是否与装箱单上一致
305 检查所有的箱子有没有外部损坏。
如果有不正确的运输导致的明显外部损坏,请立即联 质量部门。
Copyright 2010 INVENT IO AG
Page 16 - 288
Schindler 3300 AP
INVENTIO AG
Installation
K 609761 ZH / 06
设备存贮 确保货物存放在一个整洁、干燥,安全的区域,并符合下列要求:
周围无可燃性物体
在存储区不得进行气体切割等易燃操作
箱子必须放在搁板上以防水
排水沟不能堵塞
人员车辆来往较少
防止垃圾杂物
用帆布或塑料布保护
建筑物必须有防盗设施
若有叠放箱子的需要,轻箱子必须放在重箱子上
货物存放在工地之外时亦应该完全符合上述原则。
Caution!
导轨上方不得放置任何物品。
电梯部件不得露天堆放,否则违反了供货保证,使公司冒赔偿的风险。
注意 !
运输和存放导轨必须如下图所示印特别当心。导轨一般以捆供货,用叉车或吊车搬
运。
导轨搬运
1.8 m
1.8 m
2.8 m
例. 导轨搬运与
存贮
Copyright 2010 INVENT IO AG
Page 17 - 288
Schindler 3300 AP
INVENTIO AG
Installation
K 609761 ZH / 06
Caution!
电梯部件在现场的运送必须十分小心,确保不造成任何损坏,特别是导轨,不
可用机械装置拖曳,必须用适合的设备吊运。
当笨重货物运经路面时,须得到建筑商的许可,以确认路面是否牢固,能否承
受部件重量。必要时,路面须加铺垫以支撑重量。
始终遵守安全吊运规则。工程监理不得 许在无熟练工监督操作的情况下,让
新手执行吊运操作。
只 许适当的吊运设备。吊运部件必须使用安全牢固的吊索和吊运设备,并经
工程监理的检查认同。起吊重量不得超过承重梁或起吊工具的承重能力。
3-4-2 装箱描述
Note!
Schindler 3300 AP 将一次性发运到现场。所有货物根据装配情况、部件分组进行
分类包装。
装配 内容
机械部件1 对重框&附件, 轿厢立柱 , 底坑组件& 附件, 对重保护屏 , 轿厢结构后
MECH1 壁斜拉条, ACLA 或OLEO 缓冲器, GBP 限速器支撑,绳,和张紧装置.
连接板,底坑爬梯,井道分隔梁
机械部件2 MECH2 机组支撑架, 导轨支架, OLEO 缓冲器
导轨 RAILS 轿厢和对重导轨
厅门 DOOR 厅门, 顶层厅门和LDU 框架
机组 DRIVE 机组包括接线, 固定附件
轿厢 CAR 带设备&接线的轿厢下梁,护脚板,GBP 限速器,轿底板
对重块 GGW 对重块
轿顶及轿底 ROOF & 带设备& 接线的轿顶,装潢轿底,极限开关KNE
FLOOR
前壁 FRONT 轿厢前壁系统, 地坎, 门机
电气及钢带 厅门控制单元 (控制柜),
井道控制单元, 变频器, 电源接线, 井